Thursday, May 03, 2007

Dental School : 

  • Zimmer continues removing auditorium chairs and wall facings in the two auditoriums on the 4th floor of the Administration Building.
  • Boe-Tel is installing conduit for the new network cable at each bay in the 4th floor of the Clinic Building.
  • C & R Network Communication visited with Boe-tel to discuss and prepare for the next phase of the network infrastructure upgrade.  They talked with LSUHSC Computer Services about some changes on the 1st floor.
  • Coastal Air Balance started testing the hot water supply and return on the 5th floor today.
  • AT&T/Sprint tested the cell tower equipment in the penthouse for the weekend at Jazz Fest.
  • Bert Leveau Boiler and Mechanical Construction Company provided an orientation to LSUHSC Facilities staff on the hot water heaters in the basement of the Clinic Building.
  • Frischertz Electric continues with the power installation for the passenger elevators in the Administration Building penthouse.

1542 Tulane Ave. :

  • Ordes Electrical is installing motor control panels for the heating hot water circulating pumps.  
  • Arc Mechanical is performing the hydrostatic testing on the chilled water Energy Transfer Stations.
  • Stratos Elevators continues to install safeties on Elevator #3.

Irrigation Project:

  • Arc Mechanical installed three backflow preventers.
  • LSUHSC Facility Services personnel have completed the installation of 4 additional stations including the stations at the Memorial Bench.  This includes installation of the sprinkler heads.