Dental School :

  • The first phase of the environmental remediation project is underway. 
    • Zimmer is working throughout the 1st thru 4th floors of the Administration Building completing the wipe down. 
    • They are also working in all stairwells in the Clinic Building from the 1st thru the 8th floors.
  • Frischhertz shut down the building power temporarily to make the power connection to the panel in the penthouse for the new elevator disconnects.
  • Boe-Tel continues to install the cable trays on the first floor.
  • C&R Network Communications has started connecting the 300 network ports on the 5th floor of the Clinic Building.

1542 Tulane Ave.:

  • Ordes Electrical installed the motor control panels for the hot water return pumps.
  • Stratos Elevators is still installing safety equipment on Elevator #3.
  • Arc Mechanical is reassembling the ETS cabinets.  They were disassembled for the hydrostatic testing which has been completed.

Irrigation Project:

  • All of the vacuum breakers have been installed. 
  • Water is now running in two of the irrigation zones.