Dental School :

  • Edmondson Equipment is removing the debris from the 3rd floor areas that have been demolished for the new Central Sterilization room.
  • Landis has all of the new ceiling tile installed on the 2nd floor of the Clinic Building except at the sprinkler heads. 
    • They have started the installation of the border tiles on the 3rd floor.
  • Frischhertz is reinstalling the existing lights on the 3rd floor following Landis who is installing the ceiling grid and ceiling tile.
  • Firetrol continues to reposition and add sprinkler heads as necessary to accommodate the new ceiling grid.

1542 Tulane Ave. :

  • Arc Mechanical continues installing the domestic hot water pumps. 
  • Stratos Elevator is running the final tests on Elevator #3 in preparation for the visit by the State Elevator Inspector.
  • Ordes Electrical continues running wire to the transformers in vault.