Tuesday, June 12, 2007 Dental School :
-
MCC
is installing the replacement flex duct on the 3rd and 4th floors of the Clinic
Building.
- Frischhertz
is removing old conduit from the 3rd floor area where the new Central Sterilization
unit is being constructed.
- Zimmer
is cleaning the duct work on the 8th floor of the Clinic Building.
- Boe-Tel
pulling network cable from the 1st floor up to the 2nd floor into the Clinic
cubicles.
- They
are also removing the old network cables before Landis closes up the ceiling.
-
Landis
continuing installing the new ceiling grid and any of the cut tiles on the 3rd
floor of the Clinic Building.
- They
started the grid installation on the 4th floor.
- The
demolition of the central sterilization project area continues.
1542
Tulane Ave.:
- Ordes
Electrical is installing disconnect panels for the condensate return pump.
- Stratos
Elevators is installing the floor call buttons. The replacement controllers
for Elevators #7 and #8 were received on site today.
- Arc
Mechanical is installing the heating hot water pumps.
Downtown
Campus Landscaping Project: - 25%
of the sprinkler zones for the Lions/LSU Clinic Building and the CSRB are
operational. Another 25% are wired and waiting for sprinkler head
installation.
|