Louisiana State University Health Sciences Center Administration & Finance
 

Friday, June 15, 2007

Dental School :

  • The Central Sterilization structural demolition is nearing completion.
  • The installation of the ceiling grid continues on the 3rd, 4th, and 5th floors. 
    • Ceiling tiles are being installed on the 2nd floor.
    • Flex duct and supply diffusers are also being installed on the 2nd floor.
    • Frischhertz is re-installing lights on the 3rd and 4th floors. 
    • They are also making repairs to the damaged junction boxes and conduit on the 5th floor.
    • Firetrol continues to reposition and add sprinkler heads as necessary.
  • Zimmer continues to clean on the 8th floor of the Clinic building and on the 2nd through 4th floors in the Administration building. 
  • The new network and data cables continue to be run by the contractor. 

1542 Tulane Ave. :

  • Ordes Electrical is running conduit to the disconnect panels for the air compressors and the air driers.
  • Stratos Elevators continues the installation of the floor call buttons.

Landscaping Project:

  • All of the irrigation zones around the CSRB are complete, fully operational and are on auto via the controller.

Cafeteria Remodeling:

  • The 2nd portion of the terrazzo flooring has been poured.