Louisiana State University Health Sciences Center Administration & Finance
 

Monday, June 18, 2007

Dental School :

  • The structural demolition needed for the Central Sterilization installation is complete. 
    • The electrical and mechanical demolition has begun. 
  • The installation of the new ceiling grid is nearly complete on the 3rd and 4th floors of the Clinic Building and continues on the 5th and 6th floors.  
    • Ceiling tile installation is nearly complete on the 2nd floor and has started on the 3rd and 4th floors of the Clinic Building. 
    • Supply diffusers continue to be installed on the 2nd floor.
    • Landis has begun their cleanup on the 2nd floor of the Clinic Building.
  •  Frischhertz is re-installing lights on the 3rd, 4th and 5th floors of the Clinic Building. 
    • Repairs to the damaged junction boxes and conduit on the 5th floor are complete.
  • Firetrol continues to reposition and add sprinkler heads as necessary on the 3rd and 4th floors of the Clinic Building.
  • Boe-Tel continues to run network and data lines.
  • Zimmer has completed the remediation/cleaning of the 2nd through the 4th floor of the Administration Building .

1542 Tulane Ave.:

  • Arc Mechanical started the installation of new pipe to the condensate pumps.
  • Stratos Elevators was testing Elevator #3 and installed a safety chain. 
  • Ordes continues running conduit between the new 480V panels and the switchgear.

Landscaping Project:

  • 62 juniper plants were planted around the flag pole area of Lions/LSU Clinic Building.

MEB Cafeteria Remodeling:

  • Significant portions of the drywall have been installed on the new stud walls and the ceiling fur downs.