Thursday, June 07, 2007 Dental School :
- Entergy experienced a power outage in the neighborhood that includes the Dental School Campus today. Power had not been restored as of approximately 3:30 PM.
- Zimmer was working on duct cleaning, but left the site when power was lost.
- Firetrol is still adding and relocating sprinkler heads in the Clinic Building. They were able to continue working in spite of the power outage.
- Boe-Tel is still pulling network wiring on the 2nd, 3rd, and 4th floors in the Clinic Building. They also continued to work the entire day.
- Landis had the water to the Clinic Building shut down for work required in the new Central Sterilization area.
- Schindler is still working in the elevator pits in the Administration Building .
1542 Tulane
Ave.:
- Stratos Elevator is installing the controller on Elevator #3 that stops the car for each floor.
- Arc Mechanical continues installing the heating hot water pumps in the basement.
- Ordes Electrical is still pulling wire for the added transformers in the vault.
Downtown Landscaping:
- The break in the weather has allowed the installation of the irrigation system in the front of the Lions/LSU Clinic building to get back underway. Trenching was completed and most of the water lines were installed and connected.
|