Louisiana State University Health Sciences Center Administration & Finance
 

Monday, July 02, 2007

Dental School :

  • The new ceiling grid and tile has been installed throughout the majority of the 2nd  through the 7th floors of the Clinic Building.
  • New ceiling grid is being installed in the 2nd through the 4th floors of the Administration Building and in the breezeway.
  • Ceiling lights are being removed from the Library.
  • The remediation contractor is prepping Stairwell A for the anti-microbial coating application.
    • Sample results for the remaining AHU's are expected this week.
  • Boe-Tel continues to terminate the new network cable throughout the Clinic Building.
  • The walls have been framed and the sheetrock has been installed in the 2nd and 3rd Clinic Building closets.
  • The project to restore the exterior site lighting and power to the parking lot control systems has begun. 
    • New cables are being run to the light poles.

1542 Tulane Ave.:

  • Ordes checked the rotation of auxiliary compressor #1 and made the needed adjustments. 
  • Ordes installed  two 110V feeds for the drain valves of auxiliary compressors #1 & #2. 
  • Stratos Elevator is removing the cab from Elevator #2.  
  • Arc Mechanical is installing two condensate return valves and a trap to the main condensate line in the basement pipe chase.

Cafeteria Renovations:

  • Workers are installing additional drywall; fitting it into the more complicated areas of the new wall design.

Landscaping Project:

  • The edging was laid out and installed in the large planting bed on the Bolivar St. side of the Lions/LSU Clinic Building.
    • The surface was hand raked to prepare it for planting.

Parking Lot Paving:

  • Student Lot #2 has been graded and the surface has been sprayed with tar to prepare it for the application of the 1st layer of asphalt.