Louisiana State University Health Sciences Center Administration & Finance
 

Monday, July 9, 2007

Dental School: 

  • The installation of the new ceiling grid is continuing on the 8th floor of the Clinic Building and on the 3rd floor of the Administration Building.
    • Fire sprinklers are being repositioned on the 7th and 8th floor of the Clinic Building as the grid is installed.
    • Landis has a crew working on the 2nd and 3rd floors of the Clinic Building cleaning up after the completion of the ceiling tile installation. 
  • The walls for the Central Sterilization unit on the 3rd floor of the Clinic Building have been laid out and the old floor penetrations are being leveled prior to the walls being erected. 
  • The remediation contractor has completed painting Stairwell A with an antimicrobial paint. 
    • The old security office is being prepped for cleaning.
  • The terminations of the new network cable continue throughout the Clinic Building.
    • New cables are being run throughout the 2nd floor of the Administration Building.
  • New carpet is being installed on the 2nd and 3rd floors of the Clinic Building, replacing old and damaged carpet that was removed and discarded. 
  • The new fire door frames continue to be installed and secured on the 1st floor of the Clinic Building. 

1542 Tulane Ave.:

  • Arc Mechanical installed a filter on the auxiliary air compressor #2 and connected some piping to the main air compressor. 
    • They also installed a new solenoid valve on the existing surge tank. 
  • Ordes continues to run conduit and electrical wiring to the guard station.  

Landscaping Project:

  • The crews have completed the sod installation at the Lions/LSU Clinic and most of the CSRB loading dock area.