Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, August 14, 2007

Dental School : 

  • The work on the 1st floor of the Clinic Building continues.
    • The electrical and lighting installation continues.
    • The drywall installation is nearly complete.
    • The installation of the temporary ductwork is nearly complete.
  • The ceiling tile and utilities are being installed in the Central Sterilization area.
  • The installation of carpet continues on the 2nd floor of the Administration.

MEB Duct Cleaning:

  • The duct cleaning continues on the 2nd floor.

1542 Tulane Ave. :

  • Ordes Electrical is installing the disconnects for the condensate pump.
  • Stratos Elevator is still working on the installation of the travel cable on Elevator #2.
  • Arc Mechanical continues to pipe in the domestic hot water heaters.  
  • Siemens continues to install the new fire alarm panels in 1st floor security office.