Tuesday, August 14, 2007 Dental School :
- The work on the 1st floor of the Clinic Building continues.
- The electrical and lighting installation continues.
- The drywall installation is nearly complete.
- The installation of the temporary ductwork is nearly complete.
- The ceiling tile and utilities are being installed in the Central Sterilization area.
- The installation of carpet continues on the 2nd floor of the Administration.
MEB Duct Cleaning:
- The duct cleaning continues on the 2nd floor.
1542 Tulane Ave. :
- Ordes Electrical is installing the disconnects for the condensate pump.
- Stratos Elevator is still working on the installation of the travel cable on Elevator #2.
- Arc Mechanical continues to pipe in the domestic hot water heaters.
- Siemens continues to install the new fire alarm panels in 1st floor security office.
|