Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, August 15, 2007

Dental School :

  • The duct work installation continues on the 1st floor of the Clinic Building .
    • The 1st floor fire panel annunciator was moved to its temporary location near the elevator lobby.
    • Landis will begin leveling the floor in area 1 this week.
    • The drywall installation is nearly complete.
  • The new flooring was installed in the Central Sterilization area where the sterilizers will be located.
    • The rough in of the electrical outlets and switches is complete. 
    • The installation of the new duct work and diffusers is complete. 
    • The ceiling grid is completely installed and the new ceiling tile is being installed.
  • Carpet installation on the 2nd floor is nearly complete (except for the areas that are receiving a different carpet).
    • The 4th floor Auditorium C is being prepped for the carpet installation which is planned to begin tomorrow.
  • The test of the emergency generator is scheduled for this evening at 6:00 PM.  This is in preparation for the inspection by the State Fire Marshal.
    • The inspection of the fire sprinkler system is scheduled for tomorrow.

1542 Tulane Ave.:

  • Ordes connected the electrical power to the guard station in the L & M lot.
  • Arc Mechanical completed the piping fabrication for the water heaters and is working to complete the installation. 
  • Stratos Elevator Company continues to install the travel cables for Elevator #2.
  • Siemens continues to work on the fire alarm system; pulling new wires into the fire alarm cabinet.

Landscaping Project:

  • Crews completed the installation of the short sleeves on the Bolivar St. and Gravier St. sides of the MEB and the Allied Health/Nursing Building.