Louisiana State University Health Sciences Center Administration & Finance
 

Friday, August 17, 2007

Dental School : 

  • Phone and data lines were dropped near temporary guard station located on the 1st floor of the Clinic Building.
    • The air handling unit connections in area 1 and 2 are nearly complete.
    • The area 3 mechanical room floor has been completed.
    • The floor was sanded and the 1st coat of sealant was applied. 
      • Additional coats will be applied and buffed near the end of the 1st Floor Clinic Building project.
  • The sterilizers will be moved into position on Monday.
  • The installation of light fixtures and the electrical rough-in in the new network/telcom closets continues. 
    • The contractor is still waiting for the doors to be delivered.
  • Carpet installation in Auditorium C continues.
  • The curbing at the base of the stairs near the pay parking lot has been repaired.
    • Other walking surfaces are being repaired as needed.

MEB Duct Cleaning:

  • The 5th floor duct cleaning continues.

1542 Tulane Ave. :

  • Ordes installed the new fuses for the 2nd leg of the 4th floor riser.
    • The contractor also completed the power connections for the guard station in the L & M lot.
  • Stratos  completed the installation of the travel cables for Elevator #2.
    • The phone line for Elevator #2 was run to the elevator control room.