Louisiana State University Health Sciences Center Administration & Finance
 

Monday, September 10, 2007

 

Dental School :

  • 1st Floor
    • Lighting and electrical continues to be installed.
    • Mechanical room in area 3 is complete except for the electrical.
    • Rough-in for furdown is complete.
    • Sprinkler heads continue to be installed.
  • Sterilizer
    • Equipment installation continues
  • Miscellaneous
    • Natural gas lines are to be repaired and tested. Until then, propane will be used in labs.

 

1542 Tulane Ave :

  • Ordes Electric continues to run new control wiring for the flow meters, temperature sensors, & starter controls.
  • Stratos Elevator Co continues to work on elevator #2 wiring the controller in the penthouse.
  • Arc Mechanical is on site installing the air dryer for the main air compressor. Also, they are making final connections to the water heaters.
  • Arc Mechanical is constructing the wooden form for the generator foundation.
  • American Sprinkler Co is on site repacking the existing valves on the fire pump that were not corroded by the flood waters.
  • Siemens is on site installing fire alarm device boxes on the 2nd & 3rd floors.

 

Landscaping Project:

  • Completed two inch irrigation main to the front door of Allied Health. Started removing old vegetation on the Gravier St. side of Allied Health.