Dental School :

  • 1st Floor
    • Build out continues with light fixture installation and wall finishing.
  • Sterilizer
    • Installation is nearly complete and Getinge is waiting for electrical drop to be installed.
  • Miscellaneous
    • Site lighting project is progressing.
    • Asbestos survey for barracks to be demolished was completed. Sample results and demolition plan is expected soon.

1542 Tulane Avenue :

  • Ordes continues to install new control wiring.
  • Arc Mechanical completed the construction of the wooden form for the generator foundation and is scheduled to begin pouring the concrete on tomorrow, weather permitting.
  • Stratos Elevator Co. continues to wire the control panel for elevator #2.
  • Siemens continues to work on the installation of fire alarm device boxes on the 3rd floor.

Landscaping Update:

  • Completed the removal of the dead vegetation on the Gravier Street side of Allied Health and Nursing.