Louisiana State University Health Sciences Center Administration & Finance
 

Friday, September 14, 2007

Dental School :

  • 1st Floor
    • Sheetrock installation on the fur down continues.
    • Siemens is completing the installation of the VAV boxes on the air handler for area 3.
    • Electrical connections are nearly complete in the mechanical room in area 3.
    • Air handling units, light fixtures, and outlets should have power by early next week.
    • Sheetrock installation for reception desk began today.
  • Sterilizer
    • Landis has completed their work and the architects will do their walkthrough either today or Monday.
    • Getinge is working on their last few connections and should be ready for equipment testing sometime next week.

1542 Tulane Ave :

  • Ordes continues running new wiring for the EMS controls.
  • Stratos Elevator Co continues to work on elevator #2, installing new buffers and making final programming adjustments for the elevator car & controller.
  • Arc Mechanical was on site pouring the concrete foundation for the emergency generator.
  • Siemens continues to work on the fire alarm system, installing fire alarm device boxes on the 4th & 5th floors. Also the contractor has pulled all existing device wires to the junction boxes in the riser closets on floors 1 - 8.