Louisiana State University Health Sciences Center Administration & Finance
 

Monday, September 17, 2007

Dental School: 

  • The construction of the fur down in the 1st floor elevator lobby in the Clinic Building is nearly complete and the sheetrock installation has begun in the Main Lobby area.
  • The electrical connections in mechanical room are nearly complete.
  • Getinge is nearly complete with their installation of the sterilization equipment
    • They are waiting for the last of the utilities to be connected prior to system checkout.
  • The Reverse Osmosis system has been inspected and tested.  It only needs to be flushed to be usable.

1542 Tulane Ave:

  • Ordes is on site installing the conduit for the emergency generator.
    • Conduit has been installed from the junction box in the basement to a junction box in the parking lot.
  • Siemens is on site installing the fire alarm device boxes on the 5th floor and in the basement.
  • Stratos Elevator continues to install the buffer for Elevator #2.

Cafeteria Project:

  • The new bench seating which will be installed along all the curved walls was delivered today.
    • In addition, half of the booths that will go in the center of the cafeteria and the curved booths for the platform were also received on site.

Landscaping Project:

  • Crews resumed the installation of the irrigation piping on the Gravier St. side of the Allied Health/Nursing Building.