Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, September 25, 2007

 
Dental School

  • The sheet rock installation on the reception walls in the lobby of the Clinic Building is complete.
    •  Lighting installation has begun.
    • The mechanical room systems continue to be checked out and are nearly ready to be brought on-line.
  • Landis is working on the air line installation and valve repositioning in Central Sterilization
  • Doors for the new network/telecom closets should be arriving this week and the final build out will occur once they arrive.

1542 Tulane Ave.:

  • Ordes Electric completed the conduit installation for the emergency generator.
  • Arc Mechanical is replacing the pressure gauges on the Energy Transfer Station and is making a materials list for the installation of the pre-cooler for the main air compressor
  • Stratos Elevator continues to work on getting Elevators #7 and #8 to run in inspection mode.
  • Siemens continues to install conduit to the fire alarm device boxes in the basement.