Monday, October 01, 2007 Dental
School:
- The
ceiling grid is completely installed on the lobby of the 1st floor of the
Clinic Building.
- Landis
is awaiting the materials for the curved ceiling that will be installed in the
main lobby and into the elevator lobby.
- Landis
began the electrical trim out of the lights; installing fixtures and bulbs in
the Clinic Building elevator lobby.
- The
installation of the supply grilles and return grilles for the HVAC continues
around the 1st floor spaces.
- The
wall clad granite and the storefront windows are being cleaned in the Clinic
Bldg.
- The
painters are completing the last of the punch list items in the Central
Sterilization area.
- Siemens
continues their work on AHU 1-1; installing safety devices and thermostats.
- A-1
Signs started work on the LSU School of Dentistry sign.
- They
are trouble shooting the power for the neon lights that illuminates the sign
and they are painting the existing letters.
- Schindler
continues to work on repairing the freight elevator.
- They
are currently installing the additional safety breaks and wiring the new
electronic controller.
1542
Tulane Ave.: - Ordes
installed the emergency generator power wiring between the generator and the
ATS. They will begin terminating the wires tomorrow.
- Stratos
Elevator is installing new wiring for the motors of Elevators #7 and #8.\
- They
are also installing and programming new position sensors for Elevator #2.
- Siemens
continues with the fire alarm system installation.
Landscaping
Project: - The crews finished installing 3" conduit and routing irrigation valve control wires into the first floor of MEB to the controller.
- They have completed making the control wire connections for stations 1 through 6.
|