Louisiana State University Health Sciences Center Administration & Finance
 

Friday, October 12, 2007

Dental School:

  • Landis completed the installation of the indirect lights in the 1st Floor Clinic Building lobby areas fur downs.
  • The installation of the wood veneer continues.
  • Schindler worked on the final punch list items for the cars in Elevators #6 and #7.
    • They also continued working on the door controls for the freight elevator to make the existing doors compatible with the new controls.
  • The removal and replacement of the damaged laminate wall panels on the 2nd floor of the Clinic Building continues.

1542 Tulane Ave.:

  • Ordes made all the final connections for the installation of the emergency generator and was assisted by the manufacturer (Cummins) in performing the start-up of the emergency generator.
    • The contractor load tested the emergency generator for two hours and the generator performed as expected.
  • Siemens continues to work on the fire alarm system installing new fire pump controls for the fire pump in the basement.
  • Stratos continue to make progress on the repairs to building elevators.

Landscaping Project:

  • Crews continued installing garden edging on the Gravier St. side of Allied Health/Nursing Building.