1542 Tulane Ave.:

  • Ordes continues to work on pulling wires for the electronic controller (PLC) serving the Energy Transfer Stations (ETS).
  • Arc Mechanical is on site working on the water softener.
  • Entergy Thermal turned off the steam to the building so that the leaks can that were identified during the testing can be repaired.
  • Siemens is installing the fire alarm strobes and speakers in the basement.
  • Stratos Elevator continues to work on removing the elevator cab for Elevator #8.
    • They have removed the roof and two cab walls.

Dental School:

  • The installation of the curved ceiling in the Clinic Building 1st floor lobby continues.
  • The hardware for the metal doors leading to the mechanical room, the Facilities Office and the Central Supply area is in the process of being installed.
  • Landis completed the installation of sheet rock in the Conference Room located on the 2nd floor of the Administration Building.
    • The electrical rough in for the lights and power outlets has also been completed.
    • The installation of the new duct work continues.
  • Schindler repaired the basement door for Elevator #7 in the Administration Building and readjusted the dispatcher for Elevators # 6 through #8.
    • The zone switches for the freight elevator were replaced.
    • They completed the removal of the motor controller for Elevator #4 in the Clinic Building.

Landscaping Project:

  • Crews started trenching for the irrigation piping and wiring on the Bolivar St. side of the MEB.
    • They completed about half of the trenches before the rains interrupted the work.