Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, October 30, 2007

1542 Tulane Ave. :

  • Ordes installed the contacts/relays for the Parking Garage exhaust fan starters.
  • Ordes also removed the Entergy Thermal control box-PLC- which monitors and controls the Energy Transfer Station.
  • Stratos Elevator is installing the interior door hardware for the cab of Elevator #8 and continues to remove the counter-weights and elevator cab frame for Elevator #1.
    • The contractor also is working in the penthouse wiring the controller for Elevator #7.
  • Siemens continues to finalize some speaker and strobe installations in the auditorium on the 1st floor.
  • The painting contractor is working in Stairwell D and is removing the peeling paint on Floors 6 and 7.
    • The contractor is patching the walls on Floors 8 and 9 in the same stairwell.
  • The faculty continues to clean out their offices and remove personal items on Floors 7 and 8.

Dental School :

  • The installation of the Curviture ceiling in the 1st Floor Clinic Building lobby continues. 
    • The barrel ceiling material arrived today and the installation will begin shortly. 
    • The lobby reception furniture also arrived today.
  • Landis began the installation of the acoustical ceiling in the 2nd Floor Administration Building conference room. 
  • Schindler programmed the emergency telephone lines for Elevators #6 and #7.   
    • They began the ceiling installation in Elevator #5.
    • They also ran wiring for Elevators #3 and #4 to the machine room.

Landscaping Project:

  • Flowering annuals are being planted at the Lions/LSU Clinic Building flagpoles and at the memorial bench.