Dental School:

  • Landis repositioned sprinklers and relocated sprinkler pipes that will be in the way of the new ceiling in the lobby of the Clinic Building, 1st Floor.
    • Landis began cleaning the lobby floors and the granite clad wall. 
    • They are waiting for material to install the ceiling and the wood veneer on the walls.  
  • The reverse osmosis system water is being tested to determine if the sanitization and flushing of the system was successful. 
    • If the test is positive and the system is not cleared for use, the process will be repeated.

1542 Tulane Ave.:

  • Ordes Electric grounded the emergency generator and connected the wire taps in the junction box.
    • The 110 volt power was also connected to the generator. 
  • Stratos Elevator continues to work on Elevators #7 and #8, installing the door guides. 
    • The contractor is also working on Elevator #3, removing equipment from the elevator pit. 
  • Siemens (Fire Alarm Division) is on site installing and programming the fire alarm system modules in the fire alarm control panel on the 1st floor. 
  • Siemens (HVAC/Controls Division) is on site removing the AHU control panel in the basement. 

Cafeteria Renovations:

  • The new tables and chairs are being unpacked, assembled and put into place.  
  • The electrical and data wiring in the middle section is now complete. 
    • Some of the booths and associated tables have been set in place.   
  • The solid surface counter top for the beverage, coffee and the trash area has arrived and is in the process of being installed. 
  • The trim out of the curved booths is underway.

Morgue Cooler Project:

  • The cooler panel installation continues with lights being installed in the smaller walk-in cooler.
  • One evaporator unit has been hung in the large walk-in cooler.
  • The condenser unit has been set in place and tested.

Landscaping Project:

  • The crews continued installing new plants and mulching the planting beds on the Gravier St. side of the Allied Health/Nursing Building. 