Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, December 11, 2007

1542 TulaneAve.:

  • Stratos Elevator is installing new frame rails on Elevator #1.
  • Zimmer-Eschette continues to clean the ducts on the 4th Floor.
  • The ducts on the 5th and 6th Floors passed the visual inspection.
  • The sampling in the 5th Floor duct is in progress.   
  • The contractor continues to remove carpet and debris from the 4th Floor.
  • Ceiling tile is being removed on the 5th Floor.
  • Zimmer is cleaning on the 7th Floor and is nearing completion.
  • Sample Results:
    • Duct sample results for the 7th floor passed clearance, except one section of duct that the contractor is re-cleaning.
    • The re-sampling of Suite 123 (air samples) passed.

Dental School :

  • The contract for the replacement of the roofs on the main Dental School buildings has been signed. 
    • The Notice To Proceed is being issued for January 7, 2008.
  • Landis closed in the ceiling in around the new column wraps in the Clinic Building lobby.
  • Schindler is installing the hoist way for Elevator # 3.
    • They installed a part of the new bronze frame work that the front paneling connects to.

Landscaping Project:

  • The crews completed the installation of the three irrigation stations on the S. Roman St. side of the MEB at the entrance/exit to the loading dock/service area.