Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, December 13, 2007

1542 Tulane Ave.:

  • Stratos Elevator continues to work on installing the new platform for Elevator #1.
  • Zimmer-Eschette is cleaning the fan coil units on the 4th Floor.
    • The contractor has mobilized cleaning crews to the 3rd Floor.   
    • Carpet on the 4th Floor is still being removed.
    • Zimmer continues to remove debris from the 4th Floor.
    • The contractor finished removing the ceiling tile on the 5th Floor.
    • The final cleaning is in progress on Floors 6 and 7.
    • The contractor began preparing the 1st Floor for tile removal.

Dental School :

  • Schindler continues their work on the hoist way for Elevator # 4 and the wiring for the car operator panel.  
    • They began installing the second set of grippers (brakes).
    • Work on the floor indicator for Elevator # 3 continued today. 

Landscaping Project:

  • Crews completed the final grading and activated the three irrigation stations on the S. Roman St. side of MEB at the entrance/exit to the loading dock/service area.
    • New plants will be installed on Monday.