Louisiana State University Health Sciences Center Administration & Finance
 

Friday, January 25, 2008

1542 Tulane Ave. :

  • Siemens continues to trouble-shoot the wiring on the 7th Floor.
    • The contractor continues to install the new fire alarm devices in the elevator penthouses.
  • Stratos Elevator is installing the elevator cab for Elevator #1.
  • The remediation contractor continues to seal the HVAC ducts on the 6th and 7th Floors.
  • Zimmer continues to remove debris from Floors 2 - 5 in the rear of the building.
  • The contractor continues to clean on the 2nd Floor.  Crews are working in the offices along Tulane Ave.
  • Zimmer is applying encapsulant on the 5th Floor in the middle corridor where the floor tile was removed.
    •  The 5th floor is being scheduled for visual inspection.
  • The painting contractor continues to paint in Suite 123 and is floating the walls on the 7th and 6th Floors.

Dental School :

  • Needham Roofing removed an additional 25 squares of the old roof from the north side of the Clinic Building . 
    • They removed the debris and installed the first ply of the new roof.
  • Schindler installed the front and rear of the cab for Elevator #8.  
    • Schindler also installed the car rod and lantern (direction arrows) on Elevators #3 and #4. 
    • The flooring contractor installed carpet in Elevators #3 and #4. 
    • Adco is scheduled to seal and polish the brass finishes in Elevators #3 and #4 on Monday evening, January 28th.

Landscaping Project:

  • Crews completed trenching for irrigation pipe in the Parking Lot # 2 Pocket Park.