1542 Tulane Ave. :

  • Stratos Elevator is applying touch-up paint on the elevator lobby doors for Elevator #1 and is installing the flooring in Elevator #3.  
  • Siemens continues to install new fire alarm wiring and devices along the 2nd Floor center corridor and continues the testing of all the fire alarm devices previously installed.
  • Zimmer-Eschette continued cleaning on the 1st Floor in the old section of the building on the Charity side and in the Shipping and Receiving area.
  • The contractor continues to sand and prepare the walls on the 2nd Floor.
  • The contractor finished removing the floor tile from the 2nd Floor in the old section on the Charity side of the building.
    • Crews are removing floor tile from the 2nd Floor in the old section on the I-10 side of the building.
  • The painting contractor continues to apply the finish paint around the windows and doors on the 3rd Floor in the offices along Tulane Ave. and along the center corridor.
    • The contractor is applying touch-up paint in the offices on the 4th Floor.
  • The contractor continues with the installation of ceiling tiles on Floors 1 - 7 and is trimming and installing the edge and corner tiles on the 6th Floor.
    • Ceiling tile installation in the offices on the 1st, 2nd, and 3rd Floors is complete with the exception of the edge, trim, and corner tiles.
  • Royerre Commercial Carpets continue preparing the concrete sub-floor and installing new carpet tiles on the 6th Floor in the offices along Tulane Ave. and along the center corridor.
    • The contractor began working on the 8th Floor in the offices along the center corridor.

Dental School :

  • Concrete Busters backfilled and spread sand over the HDC Building #119 and the HDC Administration Building (#138) sites.
  • Securitas installed one of the pan-tilt-zoom (PTZ) cameras in the middle of the Administration Building 1st Floor lobby and the still cameras in various locations in the lobby. 
    • Securitas also installed seven of the eight cameras in the temporary bookstore.
    • The access control card reader and magnetic lock was installed at the Clinic Building south stairwell door.