1542 Tulane Ave. :

  • Stratos Elevator is run-testing and calibrating Elevator #1.
  • Siemens continues to connect wires to the fire alarm devices on the 3rd Floor.
  • Zimmer-Eschette finished cleaning on the 3rd floor in the old section of the building on the Charity Hospital side and began cleaning on the I-10 side.
  • The contractor continues to remove floor tile from the 5th Floor in the old section on the Charity side.
  • The painting contractor continues to apply touch-up paint in the offices on Floors 5 - 8.
  • The contractor continues to float and prepare the new sheetrock on the 4th Floor.
    • The contractor continues to install new sheetrock on the 3rd Floor; replacing the drywall that was removed during remediation.  
    • The crews are floating the walls and preparing them for paint as the new sheetrock is installed. 
  • The contractor continues to trim the ceiling grid on the 5th Floor.

Dental School :

  • Durr Construction continued to remove the debris from the concrete slab of the HDC Daycare Building .

Downtown Landscaping Project:

  • Crews completed the installation of the irrigation pipe and sprinklers on the Perdido St. Side of the Residence Hall. 
  • They installed the wiring for the electric irrigation valves. 
  • The installation of irrigation pipe and sprinklers on the Bolivar St. side of the Residence Hall has started.

Exterior Lighting Project:

  • Frischhertz has started pulling the electrical cable in Student Parking Lot #1 and dressing out the poles in preparation for their installation.