Louisiana State University Health Sciences Center Administration & Finance
 

Monday, April 14, 2008

1542 Tulane Ave.:

  • Stratos is testing the fire control relays for Elevators #1, #2, and #3 in preparation for final inspection by the State Elevator Inspector. 
  • Zimmer-Eschette continues to re-clean miscellaneous areas throughout the building on various floors in the old section of the building.
  • The painting contractor finished applying the touch-up paint in the mezzanine offices.    
  • The contractor continues to trim and install the edge and corner ceiling tiles on the 4th Floor.  
  • Royerre Commercial Carpet continues to install cove base and transition strips on the 4th Floor.  
  • The Herman Miller Group delivered the last of the office chairs for the 1st through the 8th Floors today. 
  • The new ceiling lights continue to be installed on the 4th Floor.

Lions/LSU Clinic Permanent Repairs and Mitigation:

  • CMI continues to work on the framing of new interior walls on the 6th and 7th Floors. 
  • The rough in electrical work continues on the 7th Floor. 
  • The 1st Floor windows are being cleaned and repaired on the Gravier St side and Bolivar St. side of the building.

Dental School :

  • Zimmer continued breaking up the large pieces of debris and removing it from the Auto Shop (Bldg. #141) and the HDC Storage Bldg (#101).
  • Needham Roofing continued work on the Power Plant; tearing off and installing 8 squares of material underneath the cooling tower.

Exterior Landscaping Project:

  • ­Crews are removing the existing vegetation from around the new oak tree on the Perdido St. side of the MEB.

Exterior Lighting Project:

  • Frischhertz continues to install lights and pull wire for the new lights under Interstate 10 at the Residence Hall parking lot.