Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, April 22, 2008

1542 Tulane Ave.:

  • Zimmer-Eschette continues to prepare the 1st Floor side entrance and corridor in the old section of the building for remediation cleaning.
  • The painting contractor is prepping the walls and the rear stairwell on the 8th Floor in the old section of the building.
  • Royerre Commercial Carpet continues to install cove base and transition strips on the 3rd Floor.
  • Trison Construction is installing the flooring for the 4th Floor network closet.
  • The Herman-Miller group continues assembling and installing furniture in the offices on the 5th Floor.

Dental School :

  • Needham Roofing completed work on the replacement of the Power Plant roof.
    • They began loading material onto the Clinic Building roof to resume the work on the roof of the penthouse.