Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, April 8, 2008

1542 Tulane Ave. :

  • Zimmer-Eschette continues to clean the corridor and elevator lobby on the 1st Floor in the old section of the building.
  • The painting contractor continues painting the offices along the center corridor on the 1st Floor.
  • The contractor continues to trim and install the edge and corner ceiling tiles on the 5th Floor.
  • Royerre Commercial Carpet crews continue to install new carpet tiles, transition strips, and cove base on the 7th Floor.
    • They have begun installing carpet tiles on the 4th Floor.
  • Boe-Tel is terminating the station cables in the offices on the 3rd Floor along the Tulane Ave. side of the building.
  • The Herman Miller Group continues to stage and install furniture in the offices on Floors 5 through 8.
    • The contractor is currently installing furniture in the offices along the center corridor on the 7th Floor.

Dental School :

  • The repairs to Elevator #8 have been completed.
    • The State Elevator Inspector has certified the elevator for normal use. 
  • Zimmer continued to remove the debris from the demolition of the Auto Shop (Bldg. #141).
  • Needham Roofing removed 4 more squares of the old roofing material from the Power Plant roof and installed the new insulation and decking. 
    • They installed the flashing and completed the granulated 2nd ply material to the 12 squares of prepared area.

Downtown Landscaping Project:

  • The crews continued removing existing vegetation from the Perdido St. side of the MEB.