Louisiana State University Health Sciences Center Administration & Finance
 

Monday, May 12, 2008

1542 Tulane Ave. :

  • The contractor is painting the handrails in Stairwell C (Center Corridor).
  • Royerre Commercial Carpet is finishing the installation of carpet in 4th Floor offices along Tulane Ave.
  • Trison continues sealing the ceiling holes in the main corridor on Floors 2 and 3.
  • The Herman-Miller Group continues to install conference room furniture on the 4th through the 7th Floors.
  • The contractor is fire-caulking the mechanical room walls on the 2nd through the 8th Floors.

Dental School :

  • Needham Roofing installed 53 squares of the granulated cap sheet and the cut-in stripping along the perimeter walls of the Clinic Building main roof. 
    • Crews started to waterproof the pre-cast panel joints at the parapet walls. 
    • They cut out the old material, installed new backer rod, and caulked the joints on the northeast end of the building.

Downtown Landscaping Project:

  • Crews unloaded a large shipment of landscaping plants.
  • Nozzles were installed on the turf spray sprinklers on the Perdido St. side of the MEB in preparation for laying new centipede sod on Tuesday.

MEB Trash Chute

  • Zimmer completed removing all of the trash from the chute and are prepared to continue the cleaning of the entire chute.