Tuesday, May 13, 2008 1542 Tulane Ave. :
- Stratos changed the buffer for Elevator # 7.
- The contractor is painting the handrails in Stairwell C (Center Corridor).
- Trison continues sealing the ceiling holes in the main corridor on Floors 2 and 3.
- Herman-Miller continues to install conference room furniture on the 4th through 7th Floors.
- The contractor finished fire-caulking the mechanical room walls on the 2nd through the 8th Floors and is prepping the walls for paint.
MEB
Trash Chute:
- Zimmer completed the pre-treatment chemical wash last night in preparation for pressure washing the chute.
Downtown
Landscaping Project:
- The crews performed minor grading and weed removal before installing new centipede sod on the Perdido St. side of the MEB.
- Five pallets of sod were laid.
- Irrigation station #16 was activated on the automatic controller to water the new sod.
|