Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, May 29, 2008

1542 Tulane Ave. :

  • Stratos finished installing the electronic infrared door sensors for Elevator #7.
    • They are installing additional safeties to measure the cab speed.
  • Zimmer-Eschette is prepping Room 815 for cleaning.
  • RCC installed VCT in Room 114, 115, and the vestibule of the auditorium.
  • The contractor finished staining the new construction wall doors on Floors 5 through 8.
  • Hogues & Associates are installing the new corridor lights in the center corridors on the 5th and 6th Floors.
  • Premier Source Inc. finished grinding the terrazzo floor in the main corridor on the 8th Floor.
    • Crews are now polishing the terrazzo.
  • The contractor began grinding the terrazzo floor in the main corridor on the 6th Floor along Tulane Ave.

Lions/LSU Clinic Building Permanent Repairs and Mitigation:

  • The dry flood-proofing of the elevator pit that serves Elevator 2 and 3 started today.
  • CMI is working on plumbing, mechanical, electrical, sheetrock, and fire sprinklers throughout the 6th Floor.

Downtown Landscaping Project:

  • Crews completed trenching and installing sleeving under the sidewalks around the Resource Center for the irrigation 2" main pipe and valve wiring.