Louisiana State University Health Sciences Center Administration & Finance
 

Monday, June 2, 2008

1542 Tulane Ave. :

  • Stratos is installing the door guides for Elevator #7.
  • Trison finished painting the installed ceiling tiles on the 1st Floor.
  • Premier Source Inc. finished polishing the terrazzo flooring on the 6th Floor.
    • They are grinding the terrazzo flooring on the 7th Floor in the center corridor and along Tulane Ave.

Lions/LSU Clinic Building Permanent Repairs and Mitigation

  • The existing slab is being removed to prepare for the construction of the new exterior stairwell.
  • The dry flood-proofing of the pit for Elevator 2 and 3 continued.
  • CMI is working on the installation of the plumbing system, the mechanical system, the electrical wiring, sheetrock, and the fire sprinklers.

MEB 2nd Floor Lobby Renovation:

  • Zimmer began removing the old floor tiles. 
  • They completed the removal of all the storefronts.

Downtown Landscaping Project:

  • Crews completed the installation of irrigation valve control wiring around the Resource Center . 
    • They resumed installation of the 2" irrigation water main.