Louisiana State University Health Sciences Center Administration & Finance
 

Friday, July 18, 2008

1542 Tulane Ave. :

  • The elevator contractor continues to work on replacing the hoist cables for Elevator #7.   
  • The front door frames have been cleaned. 
  • Securitas is preparing to install the new card readers and hardware at locations around the 1st Floor.
  • The contractor continued installing suspended ceilings in several offices.
  • Plumbers repaired pipes that serve the restrooms in the rear (oldest) section of the building.

 

Residence Hall Lobby Expansion:

  • Installation of the new duct work connecting to the AHU on the mezzanine level is almost complete.

 

Residence Hall Walkway Resurfacing:

  • The contractor filled the center drains and leveled the area in preparation for sloping the surface.

 

MEB MDL #5 Renovations:

  • The contractor continues to modify the steel support for the new partition track.
  • They are verifying the new plumbing layout.

 

MEB Lecture Rooms A & B Enhancements:

  • Facility Services has completed their portion of the work.

 

Library Commons:

  • Work continues on the construction of the bulk head that runs the length of the new Commons area.
  • Work on roughing in the electrical service continues. 

 

Duct Cleaning:

  • The crews finished the duct cleaning on the 5th Floor of the CSRB.
  • They have mobilized to the 4th Floor.