Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, July 3, 2008

1542 Tulane Ave. :

  • Siemens continues installing duct mounted smoke detectors in the HVAC ductwork.
  • The contractor finished painting Room 100.
  • Securitas continued pulling wire through the new conduit that has been installed for the card readers on the 1st Floor.
  • Hogue & Associates continued removing ballasts from old light fixtures and disposing of the old fixtures.
  • Premier Source Inc. is honing the terrazzo flooring on the 4th Floor in the Tulane Ave. corridor.

Downtown Campus Fence:

  • US Fence & Gates removed the existing chain link fencing enclosing Student Parking Lot #2 along Bolivar Street .
  • They are replacing it with new 6-ft black vinyl coated chain link fence.

Lions/LSU Clinic Building Permanent Repairs and Mitigation:

  • CMI has formed up the walls in the elevator pit in preparation for pouring concrete.
  • CMI is installing steel beams that will support the elevated pump room floor on the 2nd Floor.
  • Air handling unit components were delivered and lifted into the 1st Floor mechanical rooms. 
    • CMI is assembling and piping in the new unit in the S. Prieur St. side mechanical room.
  • CMI is installing fire retardant blocking for door frames, hanging sheet rock, and installing electrical rough in on the 6th Floor

MEB 2nd Floor Lobby Renovations:

  • Framing for the new wall panels and the electrical rough in work continues.