The initial honing of the 1st Floor hallway has been completed.
The light wells have been closed in by the contractor.
Crews continue dry proofing the enclosures.
The lighting contractor installed lights in the 7th and 8th Floor rear elevator lobbies.
Stratos Elevator is continuing to complete repair work on Elevator #4.
Zimmer-Eschette crews continue patching walls, and painting on the 5th Floor.
The demolition of the 3rd and 4th Floor annex areas is proceeding.
LSUHSC Facility Services personnel continue adjusting the old fan coil units, installing locksets, and working on maintenance items throughout the building.
Trash
Compactors:
The new trash compactors were installed at the MEB, Residence Hall and 1542 Tulane Ave.
The new trash compactor for the Dental School was delivered to the site.
Library
Commons:
The LSUHSC electricians continue to complete the electrical rough-in for the new Coffee Kiosk.
Network cables are still being pulled.
Additional ductwork is being installed throughout the floor.
Lions/LSU
Clinic Permanent Repairs and Mitigation:
The contractor continues installing door frames on the 7th Floor.
Crews continue piping in the new 6th Floor AHU on the S. Prieur side of the building.
Plumbers are roughing in the waste water and domestic water lines in Mens bathroom located on the S. Prieur side of the 6th Floor.
They are also working on the heating hot water main and branch on the east side of the 6th Floor.
Electricians are working on pulling the copper cable to run from the Entergy vault on the 1st Floor to the new switchgear on the 2nd Floor.
MEB
MDL #5:
The contractor completed the penetration for the new plumbing.
One quadrant of the new ceiling grid has been installed and the contractor continues work on the remaining quadrants.
MEB 2nd
Floor Elevator Lobby Renovations:
Electrical outlets have been moved and centered on the new wood panels.
MEB
4th Floor Ceiling Replacement:
The contractor continues installing the wall angle in the corridors.
A crew began installing sheetrock on the fur down for the tray ceiling.