Thursday, September 11, 2008
1542 TULANE AVE.:
-
General contractor continued demolition in the 3rd and 4th floor annex.
-
Elevator contractor continued work on elevator #4.
-
Security contractor continued preparations for camera installation.
-
Contractor installed support bracing for ceiling lights in the rear elevator
lobbies on 5th, 6th and 7th floors.
-
Facility Services continued installing new fan coil units on the 6th floor.
-Work continued on installation of restroom accessories throughout the
building.
-
Work continued roughing in plumbing in the 6th and 7th floor lounges for the
new kitchenettes.
-
DENTAL CAMPUS 6th and 8th FLOOR RENOVATIONS
-
Contractor continued laying-out coring locations for piping
penetrations---Coring has begun in room 8405.
DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:
-
Contractor finished removing the support beams for the accordion walls
-
Mechanical Contractor is insulating ductwork and piping in Auditorium A.
-
Contractor resumed construction of the ceiling framing in Auditorium B.
LIBRARY COMMONS:
-
Contractor continues with the plumbing for the coffee Kiosk.
-
Contractor framed the drywall ceiling above the coffee Kiosk.
-
Facilities Services continued rough in for lights.
LIONS BUILDING MITIGATION:
- Mechanical Sub-Contractor is running lines for the new Med Gas on the 6th floor
simulation rooms.
- Mechanical Sub-Contractor is running supply duct on the Gravier side of the 6th
floor.
- Mechanical Sub-Contractor is insulating the heating hot water lines on the
Bolivar/CSRB side of the 6th floor. They are also insulating the supply
duct following the installation on the Gravier side of the floor on 6 and also
on 7th floor.
- Mechanical Sub-Contractor finished raising the existing waste lines that are
below the new ceiling height on the 6th floor.
- Mechanical Sub-Contractor is piping in the waste lines and the vents for the
water closet carriers and urinals in the bathrooms on the Bolivar side of the
6th floor.
- Mechanical Sub-Contractor is piping in the AHU in the mechanical room on the
1st floor on the Gravier/Bolivar side of the building.
- Electrical Sub-Contractor is terminating the wire to the new panel boxes on the
2nd floor in the new electrical room on the CSRB side.
- Iron Sub-Contractor started erecting the steel beams for the first 2 floors of
the new stairwell.
- Contractor is painting the walls on the 7th floor of the new lab.
MDL-5 LAB RENOVATION:
- Contractor is patching wall for new paint.
- Contractor continues installing casework.
MEB 2nd FLOOR LOBBY:
- Contractor painted the ceiling of the area last night.
MEB 4th FLOOR CEILING REPLACEMENT:
- Contractor installed
supply air grilles. 80% complete.
|