Tuesday, September 16, 2008
1542 TULANE AVE.:
-
General contractor continued demolition in the 3rd floor annex.
-
General contractor placed new concrete decks in the lounges on 4th, 5th,
6th and 7th floors.
-
Elevator contractor continued work on elevator #4.
-
Lighting contractor continued installing new light fixtures in the 1st
floor Family Medicine offices.
-
Painting contractor continued painting stairwell and hallway ceilings.
-
Security contractor installed the new pan-tilt-zoom camera for the front
entry.
-
Contractor placed new concrete lids on the area ways in the front and rear
of the building.
-
Facility Services continued installing new fan coil units in 615, 616, and
617. Preparations for installation of landscaping irrigation piping commenced in
front of the building.
DENTAL CAMPUS ROOFING REPAIRS:
-
Roofing Contractor is repairing roof at wing walls of Clinic Building
and is waterproofing perimeter of Clinic roof.
DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:
-
General Contractor continues to construct framing for ceiling in Auditorium
B and is laying-out framing for ceiling in Auditorium A.
LANDSCAPING & EXTERIOR WORK:
-
Storm-toppled trees were replanted and stabilized in front of Resource
Center and Lions Eye Center.
LIBRARY COMMONS:
- Contractor framed the wall nearest to freight elevator.
LIONS BUILDING MITIGATION:
- Mechanical subcontractor is running lines for new Med Gas on the 6th
floor simulation rooms; running supply duct on Gravier side of 6th floor;
insulating heating hot water lines on Bolivar/CSRB side of 6th floor;
insulating supply duct on Gravier side of 6th floor; rerouting existing
waste lines below new ceiling height on 6th floor; installing new waste
lines from the 5th floor to the new 6th floor bathrooms on the Bolivar/CSRB
side, and piping in the AHU in mechanical room on 1st floor on the Gravier/Bolivar
side of the building.
- Electrical subcontractor is terminating the wire to new panel boxes on
the 2nd floor in new electrical room on the CSRB side; re-routing outlets
around med gas lines by the 6th floor simulation rooms; and installing
outlets in new lab area on the 7th floor.
- Iron subcontractor is welding new stairwell beams on 2nd and 6th floors on
the outside of the building on Gravier side.
MDL-5 LAB RENOVATION:
-
Contractor continues installing casework (unistrut frame), the LCD panels
display, and reinstalling air, gas and vacuum line for new casework.
-
Contractor is installing new partition panels.
MEB 4th FLOOR CEILING REPLACEMENT:
- Contractor began installing exit signs and continued installing ceiling
tiles.
RECEPTION CENTER:
- Fire Marshall Inspection is scheduled for Monday 9/22/2008 @ 2pm.
RESIDENCE HALL LOBBY EXPANSION:
- The contractor removed the temporary ramps between tower A and tower B
elevators and removed the bricks at all door entrances to make a clean
transition for the new floor.
|