Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, September 17, 2008

 

1542 TULANE AVE.:

  • General contractor continued demolition in the 3rd floor annex.
  • General contractor finished new concrete decks in the lounges on 4th, 5th, 6th and 7th floors and commenced wall construction.
  • Elevator contractor continued work on elevator #4.
  • Lighting contractor continued installing new light fixtures in the 1st floor Family Medicine offices.
  • Painting contractor continued painting stairwell and hallway ceilings.
  • Security contractor installed the new cameras at the parking garage entrance.
  • Contractor completed new concrete lids for the area ways in the front and rear of the building.
  • Facility Services continued installing new fan coil units and painting in rooms on the 6th floor.

DENTAL CAMPUS ROOFING REPAIRS:

  • Roofing Contractor is repairing roof decking on the elevator penthouse of the Administration Building - a 10ft x 10ft section of roof decking, insulation, mineral board, and roof cap sheets have been removed. The Contractor installed sheet metal and concrete to repair the deck and is re-installing the insulation, mineral board and cap sheets.

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • General Contractor has begun to construct the framing for the ceiling in Auditorium A.

DENTAL CAMPUS 6TH AND 8TH FLOOR RENOVATIONS:

  • Mechanical Contractor is installing pipe hangers and preparing pipe fittings for installation of vacuum piping in room 8405.

LANDSCAPING & EXTERIOR WORK:

  • Commenced installation of landscaping irrigation piping at 1542 Tulane.

LIONS BUILDING MITIGATION:

  • Mechanical subcontractor is running lines for new Med Gas on the 6th floor simulation rooms; running supply duct on Bolivar/Gravier side of 6th floor; insulating heating hot water lines on Bolivar side of 6th floor; insulating supply duct on Bolivar side of 6th floor; removing storm drains in the way of the duct work on Gravier side of 6th floor; and piping in the AHU in mechanical room on 1st floor on the Gravier/Bolivar side of the building.
  • Electrical subcontractor is installing outlets in new lab area on the 7th floor and running conduit to the new fire panel room on 2nd floor.
  • Iron subcontractor was welding the new stair structure on the top of 1st floor/bottom of 2nd floor; hanging steel for the new partitions on the 6th floor Gravier side.
  • Contractor is sealing penetrations on 7th floor; installing ceiling wire on 7th floor; and framing the bathroom on the 6th floor Bolivar / CSRB side.

MDL-5 LAB RENOVATION:

  • Contractor continues installing casework (unistrut frame) and LCD panels display, and is reinstalling air, gas and vacuum line for new casework.
  • Contractor completed installing new partition panels, including new door and frame, in room 4123A.

MEB 4th FLOOR CEILING REPLACEMENT:

  • Contractor installed ceiling tiles and return grille on Roman St. side.

RESIDENCE HALL LOBBY EXPANSION:

  • Contractor delivered materials and began setting up installation of self-level concrete floor.