The general contractor continued demolition in the 3rd Floor annex.
The general contractor continued wall construction in the lounges on the 6th and 7th floors.
The painting contractor continued painting hallway ceilings and began painting restrooms.
The security contractor installed new cameras that cover the driveway into the Lakeside lot.
The furniture vendor surveyed all the offices on the 5th through the 8th Floors and identified remaining rooms requiring final furniture arrangement.
LSUHSC Facility Services personnel continued installing new fan coil units.
Plumbers continued the mechanical rough-in for the kitchenettes in the 6th Floor lounge.
Crews completed clearing building supplies from the 1st Floor auditorium where they had been staged.
Electricians are trouble shooting an electrical outage on the 1st Floor center hallway.
Dental Campus Auditoriums A & B
Renovations:
The general contractor began removing the elevated flooring in Room 4203 over the weekend and continues to construct the framing for the ceiling in Auditorium A.
The electrical subcontractor continues to work overnight; attaching unistruts to the 3rd Floor ceiling in the crosswalk for the electrical and telecommunications wiring in the Auditoriums.
The mechanical subcontractor installed the chilled water pipe valves on Friday evening.
Dental School Roof Replacement:
The contractor is installing walk pads on the Clinic Building roof.
Landscaping and Exterior Work:
The crews continued installing irrigation piping in front of 1542 Tulane Avenue .
They began repairing potholes with crushed stone in Parking Lots 2 and 6 at the Dental Campus.
Library Commons:
The contractor continues to install sheetrock above the window walls.
They completed installing cementitious board on the frieze wall.
Plumbers relocated main water plumbing pipes for the coffee kiosk.
Lions/LSU Clinic Permanent Repairs and
Mitigation:
The mechanical subcontractor continues to run the new Med Gas lines for the 6th Floorsimulation rooms.
The contractor continues to insulate the supply duct along the corridor on the CSRB side of the 6th Floor;
to install piping in the AHU in mechanical room on the 1st Floor on the Gravier/Bolivar side of the building;
and to seal penetrations on the CSRB side of the 6th Floor
The electrical subcontractor is installing light fixtures for offices on the 7th Floor.
The sprinkler subcontractor is relocating sprinkler pipes on the 7th Floor.
MEB
MDL-5 Lab Renovations:
The contractor is installing wall mounted chase for the electrical and AV service for each quadrant.
The plumbing subcontractor continues connecting fixtures; working behind the casework installers.
MEB 2nd Floor Lobby Renovations:
The network wiring contractor is pulling network cable to the engineering office.
MEB 4thFloor Ceiling Replacement:
The contractor is installing ceiling tiles on the Bolivar Street side of the building.
RESIDENCE
HALL LOBBY EXPANSION
The flooring subcontractor is placing self-leveling concrete on the floor toward the Tower B elevator on the S. Roman Street side of the building.