The general contractor began the repair of the ceiling grid in the front hallway on Saturday.
Crews continued taping and floating the sheetrock wall in the lounge on the 5th Floor.
The demolition of a cool room on the 5th Floor has started.
Drywall repairs continue to be made in various offices on the 3rd Floor.
The elevator contractor is making final preparations for the formal inspection of Elevator #4.
The electrical contractor continued installing new light fixtures in Conference Room 728.
LSUHSC Facility Services repaired locks on the exterior loading dock doors and continued piping in connections for the new landscape irrigation.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor continues framing the new walls in Auditoriums A & B.
The electrical subcontractor continues to install junction boxes and to mount hardware for the ceiling light fixtures in Auditorium A.
The insulation subcontractor is labeling the HVAC piping.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The domestic water lines were successfully capped in Rooms 6333 and 6335.
DENTAL
CAMPUS ROOF REPLACEMENT:
The contractor continues installing cap sheets over roofing sheets marred by foot traffic.
The contractor is removing excess materials from the jobsite.
LIBRARY
COMMONS:
The contractor painted the concrete ceiling of the Library.
Crews continued to hang sheetrock.
LSUHSC electricians ran feeds to the new electrical panel.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor is insulating supply duct on the 6th Floor Gravier St. side of the building.
They are running branch lines to the VAV boxes on the 6th Floor on the Gravier St. side.
A VAV that was in way of duct on the 6th Floor was raised.
They re-piped the raised VAV.
ID tagged the domestic hot and cold water lines and the heating hot water lines on the 6th and 7th Floors.
Crews continue installed piping outside of the elevator lobby to connect to the sump pump that will be installed in the pit of Elevator 1 and 4 and in the pit for the freight elevator on the 1st Floor.
The electrical subcontractor is installing conduit for the new breaker box on the 2nd Floor in the electrical room located on the S. Prieur St side of the building.
Conduit is being run to the new panel in the 1st Floor electrical room.
They are wiring the sump pump for Elevators 2 and 3 on the 1st Floor.
The iron subcontractor is welding the frame on the 3rd and 4th Floors and welding the saddles on the 2nd and 3rd Floors.
The sprinkler subcontractor is dropping sprinkler heads on the 6th Floor.
The contractor is sealing wall penetrations in the middle of the 6th Floor.
A crew continues installing door frames in the middle of the 6th Floor.
They are forming up the slab on the 1st Floor by the bathrooms on the Bolivar St. side.
MEB MDL-5
LAB RENOVATIONS:
The network wiring contractor has terminated all the new data cables and installed the cover plates in the main MDL room.
The contractor started working on the punch list.
MEB
2nd FLOOR LOBBY RENOVATION:
The contractor delivered the frames for the glass storefronts and the store doors.
MEB
4th FLOOR CEILING REPLACEMENT:
The contractor installed the fire sprinklers caps.