The general contractor continued making drywall repairs in offices on the 2nd and 3rd Floors.
The electrical contractor continued installing new light fixtures in restrooms, hallways and stairwells.
The construction cleaning contractor cleaned carpets on the 7th Floor overnight.
Cleaning continued on the 6th Floor and rework continued in areas that failed inspection on the 7th Floor.
All rooms on the 8th floor are complete.
Facility Services continued to work on punch list items on Floors 5 to 8.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor prepped the sheetrock on the south and west walls for the wall paneling.
The electrical contractor installed wiring for two rows of down lights in Auditorium A.
The general contractor installed insulation and sheetrock on the north, east, and west walls in Auditorium B.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The insulation contractor insulated the supply duct on the south side of Room 8405.
The mechanical contractor installed horizontal gas piping in the walls of Rooms 8405D and 8405G.
EXTERIOR/LANDSCAPING:
Facility Services completed grading the area on the right side of the steps in front of 1542 Tulane Avenue .
The crew started installing landscape edging in the large area to the left of the steps and adjusted sprinkler head heights to coincide with the final grade.
LIBRARY
COMMONS:
The contractor installed fire sprinklers in the lounge near the windows and mudded sheetrock in the multi-media rooms.