Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, October 30, 2008

 

1542 TULANE AVE. :

  • The general contractor continued drywall repairs in offices on the 2nd, 3rd, and 5th Floors.
  • The electrical contractor completed installing light fixtures in the stairwells and continued installing new light fixtures in the 5th to 7th Floor conference rooms. 
  • The furniture vendor arranged furniture in offices on the 5th and 6th floors.  All offices planned for first phase occupancy on the 5th to the 8th floors are furnished. 
  • The construction cleaning contractor continued cleaning on the 6th Floor.
    • All rooms on the 7th Floor are complete.  
  • Facility Services continued to work on punch list items on Floors 5 to 8.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The general contractor prepped the sheetrock on the south and west walls for the installation of the new wall panels in Auditorium B. 
  • The electrical contractor installed conduit for the remaining rows of down lights in Auditorium A. 
  • The general contractor installed insulation and sheetrock on the south wall in Auditorium B.

 

DENTAL CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:

  • The mechanical contractor installed horizontal vacuum piping in the walls of Room 8405G.
  • The general contractor framed up the eastern exterior walls.

 

EXTERIOR/LANDSCAPING:

  • Facility Services completed installing landscape edging and starting installing plants in front of 1542 Tulane Ave.

 

LIBRARY COMMONS:

  • The contractor installed fire sprinklers in the Mens restrooms and installed a fire rollup door in the elevator lobby.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The electrical subcontractor installed electrical receptacles for casework along the Bolivar Street wall.
    • A crew installed wire mold for the electrical receptacles on the peninsulas along the Gravier Street side. 
    • They mounted a cabinet for a new electrical panel in the 2nd Floor mechanical room.
  • The mechanical subcontractor installed vacuum, air, & gas pipe connections to the island across from the fume hood.
    • They installed exhaust duct connections for the fume hood and installed the backsplash for the same island.
    • They also installed the remaining shelves and racks on the peninsulas along the Gravier Street side on the 7th Floor.
    • Two fresh-air ducts were connected to the new AHU.
    • Another crew roughed-in plumbing for urinals and toilets in the restrooms along Bolivar St. on the 1st Floor.
  • The contractor insulated exhaust transfer duct for offices along the Gravier Street side.
    • A crew installed water resistant sheetrock for the Womens restroom ( S. Prieur St. side and floated the sub-floor for the Mens restroom.
    • They installed two door frames and five doors in offices along the Gravier St. side on the 6th Floor.
  • The iron workers welded window wall clips and handrails from top of the exterior staircase down to the 4th Floor.   
  • The sprinkler subcontractor raised sprinkler pipe in the 2nd Floor equipment room

 

MEB 4th FLOOR CEILING REPLACEMENT:

  • The contractor installed the Blue Sky wallpaper.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor installed the ceiling and floor tracks of the metal framing for the new mailboxes.