Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, October 9, 2008

 

1542 TULANE AVE. :

  • The general contractor continued taping and floating the sheetrock walls in the lounges on the 5th Floor. 
  • The painting contractor continues painting restrooms on all floors.  
  • The electrical contractor continued installing new light fixtures in offices on the 6th Floor.
  • The furniture vendor arranged new furniture in offices on the 6th Floor along the center hallway and removed packaging materials.
  • The terrazzo contractor continues honing floors on the 1st Floor by Shipping and Receiving.
  • LSUHSC Facility Services continued piping connections for the landscape irrigation.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The general contractor is constructing the new block walls for the air handling unit room.
  • Crews are framing the new ceilings in Auditoriums A & B.
  • The electrical subcontractor continues to install junction boxes and to mount hardware for light fixtures in Auditorium A.

 

DENTAL CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:

  • The electrical subcontractor is installing receptacle boxes on the exterior walls in Room 8405.

 

DENTAL CAMPUS ROOF REPLACEMENT:

  • Contractor continues installing new cap sheets over roofing areas marred by foot traffic.

 

LIBRARY COMMONS:

  • The contractor continues to hang sheetrock.
  • LSUHSC electricians are installing light fixture frames in the ceiling near the elevators.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor is insulating supply duct, VAV, and heating hot water supply and return lines by the simulation rooms on the 6th Floor.
    • A crew is running supply duct and return duct for the AHU in the mechanical room on the Bolivar St. Side of the 1st Floor.
    • They are checking the connections for the bathrooms and the VAV boxes on the 6th Floor.
    • The med gas pipe that was damaged by the sheetrock installation on the 7th Floor is being repaired and re-tested.
    • Crews continue installing piping outside of the elevator lobby to connect to the sump pump that will be installed in the pit of Elevator 1 and 4.
  • The electrical subcontractor is installing conduit for the new breaker box on the 2nd Floor in the S. Prieur St. side electrical room.
    • They are wiring the AHU located in the mechanical room on the Bolivar St. side of the 1st Floor.
  • The iron subcontractor set the stairs and rails on the 4th and 5th Floors and tack welded them in place.
    • They are welding the saddles on the 3rd Floor.
  • The sprinkler subcontractor is moving sprinkler heads on the CSRB side of the 6th Floor. 
  • The contractor is installing ceiling grid on the 7th Floor.
    • Wall penetrations on the Gravier St. side of the 6th Floor are being sealed.
    • Additional sheetrock is being hung on the 6th Floor.
    • A crew is installing ceiling wire on the Bolivar St. side of the 6th Floor.
    • They continue to install the CMU walls on the 1st Floor by the bathrooms on the S. Prieur St. side. 

 

MEB MDL-5 LAB RENOVATION:

  • The casework contractor completed the installation of laminate countertop in the main MDL room and in Room 4109.
  • The contractor is working on general cleaning.

 

MEB 4th FLOOR CEILING REPLACEMENT:

  • The contractor is completing the fire sprinkler work.

 

RESIDENCE HALL WALKWAY RESURFACING:

  • The contractor has completed four of seven sections of the stamped concrete surface.