The general contractor continued making wall repairs in Room 545 and in various offices on the 2nd Floor.
The electrical contractor installed new light fixtures on the front porch and continued installing light fixtures in conference rooms on the 2nd and 3rd Floors.
Preparations continue for installation of the new light fixtures in the 1st floor lobby.
The construction cleaning contractor continued cleaning offices on the 5th Floor and restrooms on the 7th Floor.
The mechanical contractor continued installing and insulating air conditioning ducting in the lounges on the 3rd, 4th, and 5th Floors.
Facility Services continued minor repairs on various floors.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor installed wire mesh and foam anchors for the riser seating in Auditorium A.
The contractor installed additional sheetrock in the ceiling troughs in Auditorium B.
The electrical contractor installed wiring for the down lights in Auditorium B.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The contractor caulked joints for all the exterior masonry walls in Suite 8405 .
EXTERIOR/LANDSCAPING:
Facility Services continued planting shrubs and spread mulch in the planting beds in front of 1542 Tulane Ave.
LIBRARY
COMMONS:
The contractor installed wall tiles on the frieze wall, sprinkler pipes in the mechanical room, and ceiling grid in the study area.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed eyewash and emergency shower signage on the 7th Floor.
They insulated supply air ductwork on the northeast side of the 6th Floor.
Crews insulated domestic water lines on the east side of the 1st Floor.
The steel subcontractor welded clips on the 2nd Floor and the roof of the stair tower.
The electrical subcontractor finished installing the electrical receptacles for the lab on the 7th Floor.
Another crew moved the transformer on the 2nd Floor.
The sprinkler subcontractor moved sprinkler heads on the northwest side of the 6th Floor.
They installed fire pump valves on the 2nd Floor.
The contractor installed sheetrock on the bulkhead on the northeast side of the 6th Floor.
A crew installed studs on the 2nd Floor between the electrical and telephone room and plastered the CMU walls on the east side of the 1st Floor.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor installed the new mailboxes.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The mechanical contractor installed supply ductwork for the restrooms and lobby space.
MEB
6109 & 6148 LAB RENOVATIONS:This is
a new project that will renovate a research lab at the MEB.Included in the scope of work are new
ceilings, flooring, and lab countertops.
The contractor removed ceiling grids, ceiling tiles, and HVAC grills.