The general contractor continued work on the floor of Room 545.
They painted the ceiling grid in the vending machine alcove on the 1st Floor.
Preparations continue for installation of the new light fixtures in the 1st Floor lobby.
The electrical contractor installed new light fixtures in the front hallway on the 7th Floor.
The construction cleaning contractor continued cleaning restrooms on the 1st Floor.
Crews are re-cleaning offices on the 5th Floor that have failed inspection.
The network wiring contractor completed the new data wiring on the 8th Floor.
They continued running new data wire in the 7th Floor offices.
Window glass contractor replaced broken windows on the 1st and 2nd Floor.
LSUHSC Facility Services continued minor repairs on various floors.
DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor installed foam supports and anchors for the riser seating in Auditorium B.
They and installed additional sheetrock for the ceiling troughs in Auditorium A (1 trough remaining).
The electrical contractor installed additional wiring for the emergency lights in Auditoriums A & B.
Electricians installed wiring for the step lighting in Auditorium B.
DS 6th & 8th FLOOR LAB RENOVATIONS:
The general contractor removed wood blocking from the east exterior wall in Room 8405.
LIBRARY COMMONS:
The mechanical contractor installed branch ductwork preparing for diffuser installation in the ceiling grid near the windows.
LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed the pipes for the storm drain on the street.
Crews insulated chilled and heating hot water lines on the east side of the 1st Floor.
Ductwork from the VAVs to the new supply ducts on the west side of the 6th Floor was installed.
The HVAC system on the 7th Floor was balanced.
The electrical subcontractor installed sixteen feeders for the new switchgear.
The iron subcontractor welded the brackets for the curtain wall for the granite on the east side of the 1st Floor.
The contractor installed restroom wall tiles on the west side of the 6th Floor.
They painted the marker board locations on the south side of the 6th Floor
A crew sheet rocked the areas for the recessed television monitors on the north side of the 6th Floor.
MEB 6109 & 6148 LAB RENOVATIONS:
The contractor installed new epoxy countertops, shelving support panels, and shelve brackets in both rooms.
RESIDENCE HALL LOBBY EXPANSION:
The contractor installed stud frames for a temporary wall,which will remain in place while the old curtain wall is removed and the new curtain wall is installed.
MEB 4th FLOOR CEILING REPLACEMENT:
The contractor installed the cove lights for the blue sky ceilings.