The construction cleaning contractor continued cleaning the stairwells and restrooms on all floors.
The elevator contractor continued removing the protective film on Elevator 8.
The flooring contractor installed floor tile in the kitchenettes in the 7th Floor lounge.
The furniture vendor completed installing cabinets and setting up chairs and tables in the lounge on the 7th Floor.
The network wiring contractor continued new data wiring on the 6th Floor.
Facility Services continued making minor repairs on various floors.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor finished priming the walls in Auditorium A.
The contractor framed the stairs for Auditorium B.
The mechanical contractor connected chilled water supply and return lines to the new AHUs.
DENTAL SCHOOL
6th & 8th FLOOR LAB RENOVATIONS:
The electrical contractor installed conduit for the data outlets in Room 6335.
EXTERIOR/LANDSCAPING:
Facility Services continued removing sandbags from around buildings at the downtown campus.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor insulated chill water lines, heating hot water lines, and supply lines on the east side of the 1st Floor.
They installed roof drains on the exterior stairwell tower.
Crews notched the fire door duct on the north side of the 5th Floor.
The electrical subcontractor grounded service entrance cable on the west side of the 1st Floor.
Electricians crimped 32 feeders to allow for termination to the new switchgear on the 2nd Floor.
They installed wire for the fire alarm devices on the south side of the 6th Floor.
The fireproofing subcontractor primed saddles on the 1st – 3rd Floors of the exterior stairwell tower.
The contractor taped and floated the fur downs and monitor recesses on the 6th Floor, north side.
Crews framed windows on the northwest side of the 6th Floor.
Carpenters constructed new walls on the 2nd Floor and installed CMU on the 1st Floor, west side.
MEB
MDL 6 RENOVATIONS:
The project to renovate Multidisciplinary Lab 6 has gotten underway.The renovations to this lab will follow the model established in the renovation of MDL #5.
The contractor removed existing ceiling tiles, equipment, and disconnected electrical and plumbing for demolition.