The initial re-occupation of the building began today.Materials from the Departments of Surgery, Neurology and Pathology are scheduled to be moved in today and tomorrow.
The moving contractor delivered six truck loads for the Department of Surgery to the 7th Floor.
The access control was activated for all doors.
The construction cleaning contractor continued cleaning restrooms and stairwells.
The elevator contractor continued removing the protective film on Elevator 8.
The moving contractor completed delivery of six truckloads of material to the offices on the 7th Floor.
The network wiring contractor continued running new data wiring on the 6th Floor.
Facility Services put the new lobby light fixtures in service.
They installed the sink, refrigerator and ice maker in the 7th Floor lounge.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The electrical contractor installed wiring for the riser seating and wall sconces in Auditorium A.
The general contractor floated the sheetrock ceiling and walls in Auditorium B.
The mechanical contractor installed piping for the heating hot water supply and return lines connected to the new AHUs.
EXTERIOR/LANDSCAPING:
Facility Services completed removing and palletizing sandbags from around buildings at the downtown campus.
LIONS/LSU
PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor insulated chill water lines, heating hot water lines, and supply lines on the east side of the 1st Floor.
Crews continued installing roof drains on the exterior stairwell tower.
They installed exhaust fans and curbs on the roof of the stairwell tower.
Angle stops for the plumbing fixtures in the rest rooms and the scrub sinks on the 6th Floor were installed.
The electrical subcontractor mounted current and potential transformers for Entergy monitoring in the switchgear on the 2nd Floor.
They terminated 32 feeders to the switchgear on the 2nd Floor.
Wire to provide power to the roll up fire doors on the 5th and 6th Floor was pulled.
The fireproofing subcontractor primed the saddles on the 4th – 6th Floors of the exterior stairwell tower.
The contractors continued to tape and float the fur downs and monitor recesses on the 6th Floor.
Crews framed windows on the northwest side of the 6th Floor.
They continue installing door frames in the middle of the 6th Floor.
MEB
MDL 6 RENOVATIONS:
The contractor removed ceiling tiles, chairs, disconnected electrical lines and capped plumbing lines.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor capped existing supply HVAC duct between Tower A & B and near the corner of Perdido & Bolivar Sts.