The general contractor installed ceilings in the conference rooms on the 6th and 7th Floors.
The electrical contractor completed installing new light fixtures in the 5th, 6th and 7th Floor conference rooms and completed installation of three new recessed lights on the front porch.
The sprinkler contractor installed sprinkler heads in the 6th Floor lounge.
The construction cleaning contractor continued cleaning rooms that failed inspection on the 6th Floor and continues cleaning on the 5th Floor.
Facility Services continued minor repairs on various floors.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The electrical contractor installed wall sconce device boxes on the east and south walls in Auditorium A.
The general contractor installed riser framing in Auditorium A.
DENTAL
CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:
The electrical contractor wired the outlets on the north and south walls of Suite 8405A and 8405B.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor finished installing and testing the medical air in the 7th Floor lab.
They continue to insulate supply duct on the 6th Floor, Gravier St. side.
Crews installed additional supply duct in the mechanical room for two zones on the 1st Floor AHU on the S. Prieur St. side.
Plumbers installed domestic water lines in the bathrooms on the 1st Floor, Bolivar St. side and installed thimbles in the new stairwell for the storm drain.
The iron subcontractor cleaned, ground, and finished the hand rails on the 1st through the 6th Floors in the exterior stairwell.
The electrical subcontractor installed outlets in four runs of wire mold and installed can lights on the 6th Floor, CSRB side.
The sprinkler subcontractor raised pipe and sprinkler heads on the 2nd Floor, CSRB side.
The contractor installed ceiling tiles on the 6th Floor, CSRB side.
A crew continued to install door frames in the 6th Floor simulation rooms.
Metal lathe is being installed on the CSRB side of the 1st Floor.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor installed storefront window framing for Campus Office Stores and installed columns and storefront window framing for Medical Center Stores.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor removed a portion of the curb to allow for the installation of the new automatic storefront door.